Total Demolition of two Chimneys in Sydney, NS

Given the very strict HSE requirements at play, including dust management, the demolition of the two chimneys was carried out using negative pressure, sealing the ends of the chimneys. Debris was removed from the inside to ensure zero dust emanation into the atmosphere. Once cleared, the chimneys were strategically weakened and taken down

SERVICES PROVIDED:

  • Total demolition
  • Management asbestos paint decontamination
  • Metal Reclamation/Recycling
  • Waste management
  • Concrete crushing
  • Structural engineering
  • Consulting services

VARIOUS CHALLENGES:

  • Remote site
  • Strict HSE requirements
  • Complex methodology
  • Tall structures (67 m)
  • Environmental protection
  • Hazardous materials management
  • Dust management

Back to Démex projects